What action should be taken if a load exceeds the working load limit of a rigging system?

Prepare for the NWSA Telecommunications Tower Technician 2 (TTT-2) Fall Protection and Rigging Standards Test. Practice with flashcards and multiple-choice questions, complete with hints and explanations to enhance your learning. Get ready to ace your certification!

The appropriate action when a load exceeds the working load limit of a rigging system is to ensure that the load remains secured and is not lifted. This practice is critical for maintaining safety and preventing incidents, as exceeding the working load limit can lead to equipment failure, loss of control, and potential injuries to personnel.

When loads surpass the specified limits, the integrity of the rigging equipment—such as slings, hooks, and connectors—can be compromised, increasing the likelihood of accidents. Keeping the load secured without lifting it allows for the opportunity to reassess the situation, evaluate alternatives, or implement modifications that can bring the load within safer limits, whether by reducing the load weight or employing additional or higher-rated rigging equipment.

Taking immediate action to lift a load that exceeds the working load limit, modifying the load without addressing the root issue, or instructing personnel to stand clear does not effectively address the underlying safety concerns and can contribute to dangerous situations on the job site.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy